Stone Wall Removal Permit Process
Highway Boundary Stonewall Removal Permit Process
- Obtain a permit from Public Works Department or on the website: http://www.goshenct.gov//public-works-department/files/stone-wall-removal-permit
- Bring completed permit request form with plot plan drawn by CT licensed land surveyor to Public Works Office. Your purposed worksite will be inspected, and permit fee assessed.
- The applicant is required to post a fee equal to the cost of monument setting/work, and required maps as estimated by a Connecticut licensed land surveyor. Indicate the payee with either an ‘H’ for homeowner or ‘C’ for Contractor. This fee is refundable in stages as per Town Ordinance.
- Public Works Supervisor issues permit # based on year (i.e. ’15-’16) and permit number. Work may proceed after P.W. Supervisor signs a completed permit and return a copy to the owner
- After work is completed obtain a “Highway Boundary Stonewall Permit Refund Request” form. Available on town of Goshen website or from Public Works. Fill out and remit to Public Works.
- Public Works Supervisor will inspect completed work, 50% of the permit fee will be refunded upon submission to the Board of Selectmen of a signed and sealed completed A-2 survey of the highway boundary stone wall removed, dismantled, demolished, buried or relocated and 50% will be refunded upon completion of the highway boundary monumenting and filing of the Mylar A-2 survey of the highway boundary with the Goshen Town Clerk.